Why does the 'verify' phase in a Maven build lifecycle matter in this design?

Multiple choiceMediumchapter-10-curatedpremiumtestingintegration-testing
Choose one answer
Answer and explanation

Correct answer

B. To run checks on the results of integration tests.

Why

The 'verify' phase in Maven is used to run checks on the results of integration tests to ensure that they have passed before proceeding with further lifecycle phases like 'package'.